ArabianBusiness.com - Middle East Business News
Wednesday, 10 February 2010 00:40 UAE time

YOUR DIRECTORY /

 
Print Print | Email Email | Discuss this article (0 Comments)
| Share |

The windy city

by This email address is being protected from spam bots, you need Javascript enabled to view it  on Monday, 04 June 2007
Located in the Manama business district, the Bahrain World Trade Centre comprises two 50-storey mixed-use towers. Three wind turbines are expected to provide 11-15% of the electrical needs.

The use of wind power has taken on a new form in Bahrain. Wind was traditionally used in the Middle East to cool buildings through natural ventilation wind towers, but in the newly constructed Bahrain World Trade Centre (BWTC) it will instead contribute to the electrical supply and operation. And in a world-first, the turbines used to capture the wind's energy have been fully integrated into the building structure.

Three 29-metre diameter wind turbines form the central feature of the BWTC. These are connected by nacelles to horizontal bridges, effectively tying together the two office towers of the BWTC. And at 50-storeys and 240m tall, the sail-shaped towers complete the dramatic and distinctive form of the building.

The main co-ordination issues relate to the services between the turbines and buildings.

The BWTC forms the focal point of a masterplan to regenerate an existing hotel and shopping mall in the Manama business district of Bahrain. The use of wind turbines in the project follows over three years of intensive research and development by international multidisciplinary design practice Atkins and Danish partners Ramboll and Norwin.

Story continues below
advertisement

The elliptical plan and sail-like profiles of the towers have also been carefully designed to maximise the potential of the wind turbines. The towers are orientated to face the dominant prevailing onshore wind and their shape acts as aerofoils, effectively funnelling and accelerating the airflow between them and into the path of the turbine blades. The towers taper towards the top, their changing shape balancing with the increasing wind speed at height to ensure virtually equal wind speeds at all of the turbines.

Shaun Killa, chief architect with Atkins, proposed the design solution. "From the outset the project had as the basis of design the utilisation of conventional technologies and the development of a built form that would be sympathetic to receiving wind turbines," explains Killa. By adapting standard available wind turbines the premium on the project price of including the turbines was under 3% of the total project value. This compares favourably to Atkins' researched figures, which showed that this value could be 30% when using special turbines on large-scale building integration projects.

Wind tunnel testing was carried out to confirm the movement of the air around the towers and the availability of power. The structural shape will create an S-shaped airflow, with the centre of the airflow remaining almost perpendicular to the turbine. This increases the potential for creating power with the turbines and reduces fatigue on the blades. These tests were followed by computational fluid dynamic (cfd) modelling.

Engineering predictions by Atkins show that the wind turbines can operate in wind directions of 270-360°; however caution has been applied and initial operating regimes are based on a more limited range of 285-345°. At all wind directions outwith this range the turbines will automatically switch to standstill mode.

"Vertical axis turbines are not new technology waiting to mature, but have been known for a long time. There were a number of turbine manufactures that could supply 29/30m turbines," stresses Atkins senior project manager Simha LytheRao. The turbine blades and associated equipment were supplied as a complete package by Denmark-based Norwin. And in a truly international effort, the blades were manufactured by Danish firm LM Glasfiber in their India facility; the main gear and cooling system was from Germany; the generator from Finland; the main shaft is from the Czech Republic; and the control systems were from Denmark.

"[Norwin] was involved in the project from the very start and close co-ordination took place between the designer, supplier and contractor throughout the entire construction period and this work is still ongoing," stresses LytheRao. "The basic components of the turbines are identical to the ones you would find on any normal-mounted turbine, but the key structural components have been strengthened to increase safety and to ensure building user comfort," he adds.

Norwin and the main contractor Nass Murray & Roberts (NMR) carried out the installation of the turbines. "Large-scale turbines had never been placed at this height or between buildings before, which created new challenges," stresses LytheRao. The nacelles were lifted onto the bridges using a tower crane; this was carried out in parallel with the installation of the three bridges. The installation of the rotors followed this process. "The three blades used for each rotor were assembled on the ground and the entire rotor was lifted by tower crane into its final position and bolted to the main shaft," explains LytheRao.

"The lifting was NMR's scope, but under the supervision of Norwin; Norwin did the actual installation [of the turbines] when they were lifted into place," adds LytheRao. Cabling was within the scope of the main contractor, with the connection of cables between turbines and controllers carried out by Norwin.

"The main co-ordination issues relate to the services between the turbines and the buildings, including power cables, control cables, fire detection cables and chilled water pipes. As part of the ongoing co-ordination, the different interfaces were addressed and handled with the main MEP contractor," explains LytheRao.

All MEP installation services within the buildings and bridges, including all power cables for the wind turbines, is being carried out by the main MEP contractor, an EMCO Mercury joint venture. The lead-time for the turbines was 14 months, with the installation of the final blade being carried out in March 2007. Testing and commissioning of the turbines is scheduled to be undertaken within the next six months and they are expected to be operating on a daily basis after a further six months.

The electricity produced by the turbines will feed into the general electrical supply of the development. "Comprehensive ground tests indicate that the turbines will generate 11-15% of the energy requirements of the two towers," states LytheRao. "We have assumed that the turbines will operate on average for approximately 50% of the time over one year. This is under the provision that the buildings are able to consume the produced power," he adds.


Print Print | Email Email | Discuss this article
| Share |


READERS' COMMENTS

Disclaimer: The views expressed here by our readers are not necessarily shared by ArabianBusiness.com or its employees.

Click here to post a comment


Add your Comment
All posts are sent to the administrator for review and are published only after approval. ArabianBusiness.com reserves the right to remove any comment at any time for any reason. Please keep your responses appropriate and on topic.
Arabian Business would like to point out that only comments relevant to the story will be published. Any containing personal insults or inappropriate language will not be approved.
Name *
Remember me on this computer
Email *
(Your email address will not be published)
City
Country
Subject *
Comment *
Notify me of further comments


Please click post only once - your comment will not be published immediately.


MORE FROM ARABIANBUSINESS.COM

From  Current Issue

SHARE PRICE CHECK

RELATED LINKS

  1. Caterpillar»

 EMAIL ALERTS

  1. BWTC (Bahrain World Trade Center)

  2. Caterpillar

  3. Kuwait Insulating Material Manufacturing Co. (KIMMCO)

  4. Murray & Roberts

  5. Saudi Iron & Steel Company (Hadeed)

  6. Schneider Electric

  7. Construction & Industry


Tell us your story

Best of 2009 - Special Report

Think Tank

READER COMMENTS

  1. Gulf carriers ‘generation behind’ Cathay on service 11
    09 Feb ' 10 at 11:55
    I was based in Bahrain and then Dubai for many years, and flew many times on many airlines operating between the Gulf states and Asia,...   More  »
  2. Emaar continues Burj Khalifa maintenance work 06
    09 Feb ' 10 at 13:27
    Burj Khalifa is an architectural wonder and deserves accolades only. Trivial issues are being magnified by the media to tarnish Burj...   More  »
  3. UAE launches workers' rights booklet 05
    09 Feb ' 10 at 13:58
    The 'legitimate residency' does open up an issue where workers have been effectively dumped after a contract and not flown home as...   More  »

Read all user comments >

MORE FROM ARABIANBUSINESS.COM