The windy city
by This email address is being protected from spam bots, you need Javascript enabled to view it on Monday, 04 June 2007
To interface electrically with the building, each nacelle has a 225kW nominally-rated, 400V, four-pole induction, 50Hz asynchronous generator that is connected to a generator control panel inside each tower. From the control panels, separate low voltage (lv) feeders connect to the interfaces on the main lv switchboard at three substations which supply electricity to the landlord areas of the development.
"The length of the lv feeders from the generator control panels to the building electrical system interface points required careful study in order to avoid excessive voltage drop and to ensure there were no problems with harmonics and voltage disturbances," explains LytheRao.The generators are designed to start and run in an asynchronous mode in parallel with the mains electrical grid. In an outage or reduction in voltage or frequency from the power supply the turbines will be shut down.
The main plant is located in basement and ground levels and on service floors at levels 5, 25 and 39 within the towers. A new 11kV intake substation has been constructed for the development. Primary chilled water is being provided to basement-level plate heat exchangers by district cooling firm Tabreed; secondary chilled water is pumped from here to fan coil units (fcu) and air handling units (ahu) throughout the towers. "The secondary chilled water system is based on variable flow utilising modulating and on/off two-port control valves at the ahu and fcu with variable speed primary pumps," elaborates LyntheRao.
In addition to the wind turbines the building includes a number of features intended to reduce its carbon footprint. These include significant shading on the external glass facades; openable windows to allow mixed-mode operation in winter; thermal buffer zones between the outside and the air conditioned spaces; heat recovery; grey water recycling; and solar powered road and amenity lighting.
Construction of the BWTC began in June 2004, with substantial completion scheduled for the end of 2007. And following the success of the project, the concept of large-scale turbine integration in buildings is already being taken up on further developments. Atkins has been commissioned to design a 400m-high tower in Dubai which includes the technology as well as photovoltaics. Ramboll and Norwin is also currently engaged with a project in London, UK, where three smaller wind turbines will be installed at the top of the residential building Castle House.
Client representative: HAJ
Project manger: Atkins
Cost manager: HAJ
Main contractor: Nass, Murray and Roberts Joint Venture
Architect: Atkins
M&E consulting engineer: Atkins
MEP contractor: EMCO Mercury Joint Venture
Lighting designer: LDPi
Contract details
Construction start date: June 2004
Completion date: Substantial completion at the end of 2007
Suppliers
AHUs: SKM
Air conditioning: Trane
BMS: Honeywell
Cable: DUCAB
Cable management: Electrolink, KSA
Control valves: Honeywell
Controls: Honeywell
Coolant: Chilled water
Drainage: Gulf Plastic (uPVC pipes), Terrain (fittings)
Ductwork: Saudi Iron & Steel Company
Electrical accessories: Crabtree
Electrical distribution: ABB
Emergency luminaries: CEAG
Extract fans: Flakt Woods
Fan coil units: SKM
Fire alarm/detection: Edwards
Floor boxes: Ackermann
Floor grilles: MERO
Heat exchangers: Alfa Laval
HV switchgear: Schneider Electric
Insulation: Kimmco
Lighting controls: Clipsal
Luminaires: Iguzzini, Oldham, Louis Poulsen, UFO, Zumbtobel
LV switchgear: ABB
Power busbar: Schneider Electric
Public address system: NCS
Pumps: Grundfos, ITT-Lowara, Reddy Buffalo
Pressurisation: ITT-Bell & Gossett
Security equipment: NCS
Sound attenuation: Seagull Traders
Sprinklers: Tyco
Standby generation: Caterpillar
UPS: Chloride
Voice & data equipment: NCS
Water heaters: AO Smith
The three fixed, horizontal-axis wind turbines installed on the BWTC each comprise of a bridge, rotor, control gear, monitoring and safety systems, a nacelle and electrical building interface.
The nacelle is the cowling that connects the turbines to the horizontal bridges. These each include an enclosure with gearbox, brake, generator, cooling system and control systems. Each nacelle operates independently and will not be affected by the failure of another.
The turbines are a simple stall-controlled type, which is a passive way of limiting the power produced in their operation.
The control system is an industrial quality variety that was specifically evolved to control and monitor wind turbines. It can shut down the turbines in adverse weather conditions and is a web-based system that enables users to gain access to operating data remotely. It has an inbuilt independent emergency safety surveillance system to monitor possible faults.
The rotor blades are bolted on at a fixed angle and the profile is designed to ensure that when the wind speed becomes too high it will create turbulence on the leeward side of the rotor blade. This will prevent lift and stall the blade so that the power output stabilises at the maximum output.
The bridges are ovoid for aerodynamic reasons and incorporate maintenance-free bearings where they connect to the buildings to allow the towers to move 0.5m relative to each other. The bridges are shallow V in plan to account for blade deflection during operation.
• Nominal power generated is 225kW
• Stall-controlled power regulation
• 29m-diameter rotors
• Rotor speed at full load is 38rpm
• Air brake with centrifugally activated feathering tips
• Calper type, low speed mechanical brake
• Fail-safe disc, high speed mechanical brake
• The generator is a closed, 50Hz, four-pole asynchronous induction version
• Fixed yaw system
• Cut-in wind speed of 4m/s
• Cut-out wind speed of 20m/s
• Maximum wind speed for the blades is 80m/s
READERS' COMMENTS
MORE FROM ARABIANBUSINESS.COM
TOP IN MIDDLE EAST CONSTRUCTION & INDUSTRY
TOP MIDDLE EAST BUSINESS STORIES
ALSO IN MIDDLE EAST CONSTRUCTION & INDUSTRY
SHARE PRICE CHECK
RELATED STORIES
BWTC (Bahrain World Trade Center)
- Turbines will spin 50% of the time
21 Feb '09 | News - Will David Fisher have the last laugh and build his rotating tower?
17 Jan '09 | Comment - Power squandered by protection policy
13 Sep '08 | News
Caterpillar
- In the sales
12 Mar '09 | Features - A bellwether of a PMV show
8 Mar '09 | Comment - What’s your quarry?
13 Feb '09 | Features
Kuwait Insulating Material Manufacturing Co. (KIMMCO)
Murray & Roberts
- Construction giants reveal contracts gloom
12 Dec '08 | News - Habtoor JV trumps rivals for US $790 million tower
14 Jun '08 | News - Nakheel awards $790mn Trump contract
10 Jun '08 | News
Saudi Iron & Steel Company (Hadeed)
Schneider Electric
- Shaving savings
15 Sep '09 | Interviews - Access all areas
11 Sep '09 | Features - Energy review
28 Aug '09 | Interviews




