Is the extension up the Creek?

by Sean Cronin on Saturday, 14 October 2006

Apart from some obscure place in Wales where there is a river that runs uphill, water, given the choice, will generally choose to flow the other way.

And this has become a bit of an issue for the team constructing the Dubai Creek Extension, as they scratch their heads in search of a solution to the problem of crossing the 12-lane Sheikh Zayed Road.

It may seem surprising that this was not addressed a little bit earlier in the construction programme – at the start for example.

Story continues below
advertisement

But I suppose it could have been one of those situations where the bloke in charge said: “Tell you what lads, we’ll cross that bridge when we come to it.”

Now that they have come to it, the question of how to cross it does not yet appear to have been agreed.

If there was ever a time that the Sheikh Zayed Road could be doing without any more road works, it is now.

And the avoidance of any disruption to traffic on the road as a result of the Creek Extension, is what seems to have been given top priority.

That’s good news for everyone who owns a car in Dubai.

But how exactly do you bring a body of water, 500m wide at its broadest point, across the busiest road in the UAE without causing a few tailbacks?

One option would be to bring the canal underneath the road.

But that could mean it would only really be navigable for model boats, vertically challenged kayak enthusiasts and pooh sticks.

Another would be to bring the road underneath the canal, but given the existing congestion on the highway, we can probably safely rule that one out too.

Perhaps a more workable idea would be to take the canal over the Sheikh Zayed Road via a bridge and a system of locks.

At the moment, this looks to be the most likely option.

But it seems odd that a solution was not agreed at a much earlier stage than this.

This job should have been wrapped up by mid-2007.

That deadline is looking a little optimistic at the minute.

But maybe it will be worth the wait if we can look forward to ships passing overhead on the drive home in the evening.

Sean Cronin, Editor
This email address is being protected from spam bots, you need Javascript enabled to view it


“How exactly do you bring a body of water, 500m wide at its broadest point, across the busiest road in the UAE without causing a few tailbacks?”

Print Print | Email Email | Discuss this article |



USER COMMENTS (0 COMMENTS)

CLICK HERE TO POST A COMMENT

Add your Comment
All posts are sent to the administrator for review and are published only after approval. ArabianBusiness.com reserves the right to remove any comment at any time for any reason. Please keep your responses appropriate and on topic.
Name *
Remember me on this computer
Email *
(Your email address will not be published)
City
Country
Subject *
Comment *
Notify me of further comments
Security Code * Code


Please click post only once - your comment will not be published immediately.
From  Current Issue

more » MIDDLE EAST MARKETS

ASE

Last Price:

4,750.17

-4.06p-0.09%

 EMAIL ALERTS

  1. Construction & Industry



ArabianBusiness.com/Jobs - Middle East Jobs Search
  1. Resident Engineer
    Industry: Construction
    Location: Bahrain
  2. Senior Project Manager/Project Manager
    Industry: Construction
    Location: Dubai, UAE
Browse all jobs »

BUSINESS FEATURES

Louvre connection

Pritzker Prize winner Jean Nouvel is bringing the first offshoot of France's famous museum to the Gulf.

Worker conditions fall short

The UAE must provide basic wages, safety and housing for its construction workers.

Rainbow Sheikh's 'Power Wagon'

Desert and oil. These sum up the emirate of Abu Dhabi perhaps better than anything.

MORE FROM ARABIANBUSINESS.COM