Extension of time claims

by Jeffrey Badman on Saturday, 17 November 2007

In my experience, extension of time claims are unsuccessful because the contractor fails to adequately demonstrate its case through its submission of detailed particulars.

When drafting an extension of time claim, in my view, there are eight essential elements that must be addressed:

The event

Story continues below
advertisement

Identify the event: the circumstance which gives rise to change causing delay.

Liability for the event

Once an event has been identified the next step is to determine liability for the event.

If responsibility rests with the employer or it is a neutral event, such as force majeure or exceptionally adverse climatic conditions, the contractor may be entitled to an extension of time. However, this is dependent upon the terms and conditions of the particular contract. In circumstances where the contractor is responsible for the event then the consequences remain with the contractor.

Contractual entitlement

Typically, construction contracts contain provisions entitling the contractor to an extension of time on the occurrence of a particular event provided the progress of the works or time for completion is delayed as a consequence.

For example FIDIC 1987 provides for an entitlement for extension of time in the event of: late drawings (Clause 6.4); adverse physical obstructions or conditions (Clause 12.2); discovery of fossils or antiquities (Clause 27.1); additional tests not provided for (Clause 36.5) suspension of the works (Clause 40.2); failure to give possession of site (Clause 42.2); additional or extra work (Clause 44.1(a)); exceptionally adverse climatic conditions (Clause 44.1(c)), any delay, impediment or prevention by the employer (Clause 44.1(d)); any special circumstances, other than through the default of the contractor (Clause 44.1(e)); and, contractor's suspension of the works (Clause 69.4).

Contractual compliance

Generally within an extension of time clause, the contractor will be obligated to submit notice(s) and detailed particulars within a specified time frame.

For example, Clause 44.2 of FIDIC87 provides: "Provided that the engineer is not bound to make any determination unless the contractor has (a) within 28 days after such an event has first arisen, notified the engineer with a copy to the employer, and (b) within 28 days, or such other reasonable time as may be agreed by the engineer, after such notification submitted to the engineer detailed particulars of any extension of time to which he may consider himself entitled in order that such submission may be investigated at the time."

Occasionally the submission of notice and/or detailed particulars will be expressed to be a condition precedent. The contractor's failure to comply waives its entitlement to claim an extension of time and owner's liability ceases. For this reason it is important to take cognisance and comply with the notice and detailed particular provisions expressed in the contract. Familiarity with the contract from the start of the project at all levels is therefore critical.

In addition, further submissions may be required for particular events, for instance: Clause 6.3 of FIDIC 87 (disruption of progress) requires the contractor to ".... give notice to the engineer, with a copy to the employer, whenever planning or execution of the works is likely to be delayed or disrupted unless any further drawing or instruction is issued by the engineer within a reasonable time. The notice shall include details of the drawing or instruction required and of why and by when it is required and of any delay or disruption likely to be suffered if it is late."

Cause and effect

A common mistake made by many contractors when attempting to demonstrate the cause and effect of an event is that they merely list in chronological order the pertinent exchanges of correspondence between the parties. From my experience this is usually insufficient to satisfy the burden of proof. To demonstrate cause and effect, a story should be prepared based on the facts describing the effect(s) of the event upon the works. This should include details of the planned works affected, referring to the planned sequence, durations, and methodology; the status of the works in relation to that planned at the time of the event; and, description of the changes to that plan as a consequence of the event.

Delay analysis

Conduct a delay analysis to demonstrate the effect of the event on the contractor's programme.

There are a number of internationally recognised delay analysis methods. Ultimately, the choice of delay analysis methodology will be dependent upon such matters as level of records available; the robustness of the baseline programme and any updates; time available; degree of accuracy; and, level of proof required.

Statement of claim

Every extension of time claim must contain a succinct statement of what the contractor is claiming.

Substantiation

Extract and provide documentary evidence (letters, method statements, instructions, progress reports and photos, minutes of meetings, programmes and schedules), statements of fact and expert witness statements (if required) in support of the assertions made within the claim submission.

Adopting these eight elements as a check list will give a good starting point for drafting any extension of time claim, in spite of each construction project being unique.

Print Print | Email Email | Discuss this article |


READERS' COMMENTS



Click here to post a comment


Add your Comment
All posts are sent to the administrator for review and are published only after approval. ArabianBusiness.com reserves the right to remove any comment at any time for any reason. Please keep your responses appropriate and on topic.
Name *
Remember me on this computer
Email *
(Your email address will not be published)
City
Country
Subject *
Comment *
Notify me of further comments
Security Code * Code


Please click post only once - your comment will not be published immediately.


MORE FROM ARABIANBUSINESS.COM

From  Current Issue

RELATED LINKS

  1. Hill International»

 EMAIL ALERTS

  1. Hill International

  2. Construction & Industry


BUSINESS FEATURES

Paradise found?

The Al Barari development in Dubailand is positioning itself as Dubai’s least dense development.

Building with a brain

Green buildings are supposed to transform the way buildings and communities are designed.

The final frontier: Palm Deira

It might be the least talked about of the Palms – but the Palm Deira is right on schedule with its reclamation work.

ArabianBusiness.com/Jobs - Middle East Jobs Search
  1. Commercial Director
    Industry: Construction
    Location: Abu Dhabi, UAE
  2. Project Manager - Lead Architect
    Industry: Construction
    Location: Dubai, UAE
Browse all jobs »

BUSINESS INTERVIEWS

Construction boom to ease

Blair Hagkull, of Jones Lang LaSalle, MENA, on what lies ahead for the Middle East construction market.

The godfather of the Greens

David Gottfried developed the Leed building rating system and founded the US Green Building Council.

The new kid on the block

Imran Khan, CEO of Al Barakah, explains why the Ajman construction and real estate market is poised to take off.

MORE FROM ARABIANBUSINESS.COM