Tower power

by ArabianBusiness.com staff writer on Sunday, 20 April 2008

Ensuring 24/7 power supplies for the Burj Dubai has meant some unusual distribution practices. We take a look at the final systems being installed in the project.

With over 160 levels to provide with power and a connected load of 74.15MW and MD of 44.32MW, the installed electrical distribution system for the Burj Dubai is somewhat unusual for a mixed-use building.

High voltage operations

Story continues below
advertisement

The building is served by a total of twenty 11kV feeders from the Dubai Electricity and Water Authority (DEWA) network. It is also connected to a DEWA 132/11kV substation that is located within the Burj Dubai Development.

Rather than step-down transformers reducing the voltage at the high voltage (hv) incoming supply, here an 11kV power supply is distributed throughout the building via two main risers.

Two separate risers located in the building core serve the full height of the building and operate in parallel to ensure security of supply.

Supplies within the risers provide normal operating power and emergency generating power separately, with emergency generators serving the life safety systems, elevators and general escape lighting.

Five 2200kVA generators provide back-up to the life safety systems in the event of a power failure. Under total or partial power failure the generators will operate via automatic transfer switches (ATS). Battery-operated emergency lighting will also operate within the tower in the event of a mains failure.

The 11kV distribution within the risers has been completed using a four-core, 180mm2 diameter cable. This decision was made as 11kV busbars are more suitable for use in short runs within substations; the flexibilitiy of tap-off points provided by busbar was also not necessary in the building.

Low smoke and fume (LSF) cables have been specified throughout the project in order to reduce the risk of fume pollution in the event of a fire.

The hv distribution serves hv substations within the main MEP floors of the tower at levels 17, 40, 73, 109, 136 and 155. At these points the supply is reduced to 400V and distributed locally by busbar via sub-mains distribution boards. These eventually feed local distribution boards via corridor routes.

Powering up

The main DEWA substation that will serve the Burj Dubai is currently under construction and scheduled for completion around May 2008.

As permanent mains power is thus unavailable during the construction period, the building is connected to temporary power supplies and some local generators.

All hv work on the project has been installed according to Dubai Electricity and Water Authority (DEWA) Regulations, however it is effectively a private network.

The MEP contractor was partly chosen due to their skills with hv installations.

The final testing and commissioning of the systems will be carried out by a separate specialist subcontractor.

RELATED LINKS: Supplying skywards services, Servicing the Burj, Going up..., Cool runnings, Pipe plans, Fire safety at height, Making initial preparations

Print Print | Email Email | Discuss this article |



USER COMMENTS (0 COMMENTS)

CLICK HERE TO POST A COMMENT

Add your Comment
All posts are sent to the administrator for review and are published only after approval. ArabianBusiness.com reserves the right to remove any comment at any time for any reason. Please keep your responses appropriate and on topic.
Name *
Remember me on this computer
Email *
(Your email address will not be published)
City
Country
Subject *
Comment *
Notify me of further comments
Security Code * Code


Please click post only once - your comment will not be published immediately.
From  Current Issue

more » MARKET DATA

EMAAR.DFM

Last Price:

10.05

-0.05-0.50%

17 Jul 2008 09:59 GMT
(Market Closed)

RELATED LINKS

  1. Dubai Electricity & Water Authority (DEWA)»
  2. Emaar Properties PJSC»

 EMAIL ALERTS

  1. Dubai Electricity & Water Authority (DEWA)

  2. Emaar Properties PJSC

  3. Construction & Industry



ArabianBusiness.com/Jobs - Middle East Jobs Search
  1. Senior MEP Coordinator and MEP Coordinator
    Industry: Construction
    Location: Dubai, UAE
  2. Recruitment Manager
    Industry: Construction
    Location: UAE, UAE
Browse all jobs »

BUSINESS FEATURES

Garden extraordinaire

At 73% of the total area, green space dominates Dubai's Mohammed Bin Rashid Gardens project.

Taming the tiger

The Tiger Woods Dubai golf course project at Dubailand is teeing up to meet its late 2009 deadline.

Workplace fire safety

By following these simple steps you can reduce the likelihood of adding to the UAE's fire statistics.

BUSINESS INTERVIEWS

Selling paradise

Drake & Scull International CEO Khaldoun Al Tabari can’t see an end to the regional building boom.

Rotating revolution

Italian architect David Fisher discusses his plan to build Dubai's first rotating skyscraper.

Strong foundations

Raymond Debrauwer discusses a recent boom in the steel foundations market in construction.

MORE FROM ARABIANBUSINESS.COM