ArabianBusiness.com - Middle East Business News
Sunday, 22 November 2009 14:24 UAE time

YOUR DIRECTORY /

| Share |

Business development

by This email address is being protected from spam bots, you need Javascript enabled to view it  on Thursday, 18 December 2008

With so much material spread over such a huge site, there may have been serious problems and delays. However, through forward planning and easy communication between contracts ASGC and themselves, ASU seems to have it under control.

MEP construction manager on the project, Hossam Al-Bishbishy, reveals: "With the materials, from day one we have done planning to procure it on time on site.

So we started planning at an early stage to get approval from the engineers on the materials and arrange the delivery of the procurement to be on time on the site."

Story continues below
advertisement

El Wakil adds: "So far we are not facing any kind of lack of materials. For the labour as well we are coping with the progress on site. So far things are going smooth but it needs to be double or triple or more than on a regular job because we are working on so many buildings at one time."

Switchgears for the project consist in total of more than 1,300db and more than 160km of cable has been used while hooking up the electrical systems. Seven substations are supplying the development and there are also seven standby generators for the site.

The hotel will boast a complicated electrical system in each room including a home automation control in each room. These systems will be capable of controlling everything within the room including the curtains.

Despite this ASU claim that the hotel will not pose a bigger challenge than the rest of the buildings, but do admit that it could be slightly delayed compared to the rest of the development. El Wakil reveals: "It's not really a question of it being harder, this project is supposed to be completed in July 2009, including the hotel also. Maybe the hotel will be a little bit delayed till November or something."

Plumbing plant

Plumbing on the project has been challenging in the way that all of the other components of the MEP work has - the sheer size of it. El Wakil describes the work being done: "Talking about plumbing, we have a domestic water supply that consists of underground reservoirs of more than 1,000,000 gallons, pumped through 17 pump sets. Each set consists of four pumps, three on duty and one on standby.

With the drainage system we have a network of piping almost 51,000m we have 19 sets of submersible pumps."

The buildings are located only 1km away from Sheikh Zayed Road and will have a water attraction running past them. The water will just be standing water and will not be connected to the nearby extended creek. While work on the site is progressing well, El Wakil is the first to admit it hasn't been easy: "We are working on 13 projects here at the same time.

If you consider each building as a project then we have 13 subprojects so the challenge comes from providing the necessary resources, I mean labour, materials and all these things to be provided at the same time to serve the construction work that is going on all over the 13 buildings. And coping with all the necessary challenges to complete the project on date has been hard."

Business Bay is set to become one of Dubai's greatest commerce attractions, and it is ambitious developments such as Bay Square that will ensure its ambitions are fulfilled.

The sheer scale of this project would be daunting to many companies and there is a definite advantage here to ASU being part of the Al Shafar Group. Easy communication, sharing of resources and forward planning has ensured that the project, as of yet, has run smoothly.

It is rare that an MEP company is so directly linked with the contractor on a site but this case is a perfect example of the need for communication on the site. It comes easy in this case, and for good reason, but any MEP contractor about to embark on a large project such as this can see why working together with all parties is worthwhile - it makes perfect business sense.

Bay Square: Vital statistics

• Over 655,000 square feet of ducting is being used on the project

• Almost 10km of chilled water piping is to be installed

• Covers 2.4million square feet

• Seven substations will power the buildings

• More than 160km of cable is being used

• More than 300 jet fans and 1,200 fan coil units are being installed across the development

• The project has a completion date of July 2009 for all of the buildings including the hotel


| Share |


READERS' COMMENTS

Disclaimer: The views expressed here by our readers are not necessarily shared by ArabianBusiness.com or its employees.

Click here to post a comment


Add your Comment
All posts are sent to the administrator for review and are published only after approval. ArabianBusiness.com reserves the right to remove any comment at any time for any reason. Please keep your responses appropriate and on topic.
Arabian Business would like to point out that only comments relevant to the story will be published. Any containing personal insults or inappropriate language will not be approved.
Name *
Remember me on this computer
Email *
(Your email address will not be published)
City
Country
Subject *
Comment *
Notify me of further comments


Please click post only once - your comment will not be published immediately.


MORE FROM ARABIANBUSINESS.COM

From  Current Issue

SHARE PRICE CHECK

 EMAIL ALERTS

  1. Al Shafar General Contracting Co. LLC

  2. Construction & Industry


Tell us your story

READER COMMENTS

  1. RTA to lease last batch of retail outlets on Red Line 04
    22 Nov ' 09 at 11:48
    Thanks v m Joey. I heard they were proceeding with a few of them. i guess things may have changed.   More  »
  2. The Roubini Vs Rogers debate 02
    22 Nov ' 09 at 06:30
    What's not to understand.It's 1930s Hoover-Roosevelt liquidation.Are you really naive enough to believe that Andrew Mellon's...   More  »
  3. Merger technical talks to conclude in a month - Emaar 02
    22 Nov ' 09 at 11:38
    Many a owners are paying the facility maintenance fee for all the services that are supposed to be covered by the Municipality in...   More  »

Read all user comments >

Gitex 2009

MORE FROM ARABIANBUSINESS.COM