Meydan axes racecourse contract

by This email address is being protected from spam bots, you need Javascript enabled to view it  on Saturday, 10 January 2009
The $1.25 billion Meydan Racecourse contract was awarded in September 2007 and is expected to open for the 2010 Dubai World Cup.

A dispute is underway between Dubai-based Meydan and Malaysian contractor WCT after the developer cancelled the US $1.25 billion (AED4.6 billion) Meydan Racecourse construction contract last week.

In a statement to Construction Week Meydan said that the contract was cancelled because WCT "failed to abide by the time schedule for the completion."

The statement also said alternative companies were selected.

Story continues below
advertisement

But WCT, which was awarded the contract in September 2007 as a 50/50 joint venture with Dubai-based Arabtec, disagreed.

"The board views the cancellation as a breach of contract on the part of the employer," the firm said in a statement.

"The company, through the joint venture, is currently considering all its options and will take the necessary steps to protect the Group's interests."

A Kuala Lumpar-based JP Morgan analyst, who is close to WCT management, told CW that 60% of construction work had been completed, but the joint venture had only been paid for 28% of it.

"I wouldn't have been surprised had there been a re-negotiation," he said. "Either a combination of lower contract values to reflect lower pricing or a down-scoping exercise where the original contractors could do something smaller.

"What was disturbing was the announcement that the contract had been cancelled. It is a strange way to start the year for the client, the contractors and the market."

Shares in WCT took their biggest dive in 14 years on the news, sliding 30% before trading was suspended in Kuala Lumpur.

"In any construction project there are always differences between what you want to achieve and what is actually happening on the ground," a WCT spokesman said.

"Changes to the design and to the work that is to be done are always happening in every project, especially in areas like Dubai where construction is always so intense."

Arabtec chairman Riad Kamal remained tight-lipped on the subject. "Now is not really the time to discuss the reasons why the contract was cancelled," he said.

"I would rather not go into this for reasons of non-disclosure and other commitments."

Meydan said it is taking steps to commission other companies to complete the racecourse by 2010. It is aiming for completion of the course in time for the Dubai World Cup horse race.

The original contractual date for completion was October 7, according to WCT.

The contract covered construction and completion of the main building works, external works and infrastructure works of the racecourse project.


For news updates sign up for our newsletter
| Share |


READERS' COMMENTS

Disclaimer: The views expressed here by our readers are not necessarily shared by ArabianBusiness.com or its employees.

Click here to post a comment


Add your Comment
All posts are sent to the administrator for review and are published only after approval. ArabianBusiness.com reserves the right to remove any comment at any time for any reason. Please keep your responses appropriate and on topic.
Name *
Remember me on this computer
Email *
(Your email address will not be published)
City
Country
Subject *
Comment *
Notify me of further comments


Please click post only once - your comment will not be published immediately.


MORE FROM ARABIANBUSINESS.COM

From  Current Issue

SHARE PRICE CHECK

RELATED LINKS

  1. Meydan»
  2. WCT Engineering Berhad»

 EMAIL ALERTS

  1. Meydan

  2. WCT Engineering Berhad

  3. Construction & Industry



READER COMMENTS

Reader Comments (24 hrs)

  1. Is a merger best? 1
    04 Jul ' 09 at 15:29
    The comments above make one wonder why this guy is earning a tiny salary as editor of a minicule local mag for brickies when with his...  More »
Read all user comments >

BUSINESS FEATURES

Real value?

How will Emaar merger with three Dubai Holding cos affect its investors and the emirate's property market?

Top 10 billion dollar projects in Abu Dhabi

Abu Dhabi has come out on top during the economic downturn and is still forging ahead with development.

Gateway to a new Jeddah

Emaar Properties' Jeddah Gate project is leading the charge to rebuild Jeddah's city centre.

BUSINESS INTERVIEWS

Discussing the downturn

We ask a select group of key decision-makers about current issues in the construction industry.

Six tips for surviving the downturn

Find the factors that are helping some companies thrive, while others struggle.

Man with a plan

Saudi Arabia’s Deputy Minister for Town Planning discusses the economic cities and offers advice to foreign companies looking to invest.

MORE FROM ARABIANBUSINESS.COM