Saudi officials accused of delays
by Reema Memon on Saturday, 24 January 2009
Five government offices have been accused by the Jeddah mayoralty for delaying the execution of US $266.9 million (SAR1 billion) tunnel and bridge projects at 18 of the city's intersections.
The government offices are alleged to have not provided accurate and timely information on underground service lines at the project sites.
According to Dr Ahmad Banafi'a, supervisor general of projects at the mayoralty, the government offices did not furnish the required information until the design phase of projects began.
After the projects were handed over to contractors and prepared for the execution, service lines were detected in some locations. "This was contrary to the information provided to us that there were no service lines at the sites," he said.
The mayoralty stopped digging at the sites once the service lines were discovered.
The mayoralty has now been forced to undertake the task of covering the service lines which is "a complicated and a long procedure," in addition to bearing the costs.
Banafi'a said obtaining permits to stop traffic at streets adjacent to the sites of projects takes a long time.
Projects with obstructing service lines need an extended period of construction time.
READERS' COMMENTS
MORE FROM ARABIANBUSINESS.COM
TOP IN MIDDLE EAST CONSTRUCTION & INDUSTRY
TOP MIDDLE EAST BUSINESS STORIES
ALSO IN MIDDLE EAST CONSTRUCTION & INDUSTRY
LATEST MIDDLE EAST BUSINESS NEWS
- Education: Mubadala completes $1bn financing for uni project
- Banking & Finance: Deal sought on Dubai World, Nakheel debts
- Banking & Finance: Arab youth SMEs turn to family finance
- Banking & Finance: Dubai raises further $5bn in bond sale
- Transportation: Shipping slump stops Bahrain's new port signing main liner