ArabianBusiness.com - Middle East Business News
Thursday, 26 November 2009 23:12 UAE time

YOUR DIRECTORY /

| Share |

‘Swift’ arbitration is key

by Dr Chandana Jayalath on Saturday, 13 June 2009

Construction contracts often include ‘keep working provisions' for the parties to perform their obligations, despite the existence of a dispute. The contract may expressly forbid the contractor's right to suspend work or terminate the contract, although inconsistent with the local law.

For example, under English law, there is a statutory right to suspend work for non-payment, which can not be excluded by contract.

Also, the employer may have the right to require a contractor to proceed with variations despite the time and cost consequences, not having been agreed in advance. In a fixed lump sum contract, the contractor may lodge a claim for variation, but the employer might deny it upfront on the basis of ‘lump sum' or pay half of the cost pending evaluation at a later stage. The engineer may ask the contractor to go ahead with the rates he deems suitable whenever the contractor has no option, because of his obligation to complete works on time.

Story continues below
advertisement

Although the contractor is supposedly responsible for quantity errors, in any typical lump sum contract where the quantities are said to be actual and correct, he will purposely keep silent in a windfall such as overestimated quantities that bring him money for nothingAlthough the contract expressly says no re-measurement is possible, the losing party may bring out this case and attempt to interpret the function of re-measurement as the ‘standard practice'.

There is usually a term implied to the effect that the client will not prevent the contractor from carrying out work in accordance with the terms of the contract, which is sometimes referred to as the prevention principle. In the UK case of Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd (1970), some defective work was discovered before practical completion had been achieved.

The client was responsible for long delays owing to failure to approve a scheme of remedial works. A dispute arose concerning the contractor's entitlement to an extension of time. Unfortunately, there was no specific provision for an extension of time when the contractor is delayed by the client, which is a fatal shortcoming in the contract. Another aspect is that many contracts do not have a mechanism to compensate the loss behind unprecedented price escalation in the Gulf region. This is where swift solutions are required to minimise potential losses suffered by parties, instead of allowing ‘loss to prevail where it lies', particularly when contracts are silent.

Perhaps some claims are indeed necessary and the provision for making claims is essential in order to accommodate unavoidable changes, for example by granting justifiable extensions without invalidating the contract. However, problems arise when the provision is abused, for example by contractors who allegedly tender at low prices with the objective of profiting from their claims. For example, the government sector has now been bombarded by claims more than ever before.

Claims specialists have been busy with compiling claims for work suspended in recession. On the other hand, clients who attempt to aggressively suppress legitimate claims may provoke exaggerated, unjustified or even frivolous claims with the help of their in-house experts. Needless to say, the vicious circles generated by such exaggerated actions and reactions definitely add to the avoidable costs of construction.

The author therefore strongly believes in a speedy, flexible and a fair process, indeed a gentlemanly way to resolve disputes between gentlemen, as Alexis Mourre says, rather than too formal court lawyering. This is where ‘swift' arbitration comes into play in the context of construction thus minimising the legal expenses for making and breaking claims and demoting the tendency towards interim awards and temporarily-binding decisions.

Dr Chandana Jayalath is a Member of the Royal Institution of Chartered Surveyors and a senior contracts specialist for the Public Works Authority (PWA) in Qatar. His latest industrial exposure has been sidelined in the settlement of various commercial and contractual issues, claims and disputes arising in the infrastructure projects spearheaded by the PWA.

The opinions expressed in this column are of the author and not of the publisher.

| Share |


READERS' COMMENTS

Disclaimer: The views expressed here by our readers are not necessarily shared by ArabianBusiness.com or its employees.

Click here to post a comment


Add your Comment
All posts are sent to the administrator for review and are published only after approval. ArabianBusiness.com reserves the right to remove any comment at any time for any reason. Please keep your responses appropriate and on topic.
Arabian Business would like to point out that only comments relevant to the story will be published. Any containing personal insults or inappropriate language will not be approved.
Name *
Remember me on this computer
Email *
(Your email address will not be published)
City
Country
Subject *
Comment *
Notify me of further comments


Please click post only once - your comment will not be published immediately.


MORE FROM ARABIANBUSINESS.COM

From  Current Issue

SHARE PRICE CHECK

 EMAIL ALERTS

  1. Royal Institution of Chartered Surveyors, UK

  2. Construction & Industry


Tell us your story

READER COMMENTS

  1. Deal sought on Dubai World, Nakheel debts 20
    26 Nov ' 09 at 20:13
    Red Devil/Sandjocky, I have also had several posts blocked over the past couple of days, posts that speak of the facts only as they...   More  »
  2. UAE real estate market has now hit bottom - analysts 05
    26 Nov ' 09 at 21:36
    Comn' AB is a yo-yo when it comes to news.People forecasting good and then bad. Good and bad and then some more "experts" saying...   More  »
  3. Moody's cuts Dubai GRI ratings amid debt delay 02
    26 Nov ' 09 at 19:51
    Dubai World better change its slogan & reposition itself - Dubai LTD.   More  »

Read all user comments >

Gitex 2009

MORE FROM ARABIANBUSINESS.COM