by Sathya Mithra Ashok on Thursday, 02 July 2009
We have between 20 to 30 repairs in the Mediterranean Sea alone every year. – Alain Polloni, head of submarine operations and maintenance, France Telecom-Orange group.

While the rest of the world was celebrating the beginning of 2009, one France Telecom-Orange team was busy mending damaged cables, some few thousand metres under the surface of the Mediterranean Sea. Sathya Mithra Ashok gets a blow-by-blow account of how it was done.

If the average IT manager in an enterprise thinks he is having trouble with his cables, it is time for him to think again. After all, he does not have to constantly monitor and rectify faults that occur thousands of metres below water, right at the ocean floor.

"We have between 20 to 30 repairs in the Mediterranean Sea alone every year. And at least some across other parts of the world, maybe three to four repairs per year on cables that we operate. And if we see just some of the cables for which we have stations in France and, or French-overseas territories, there are times when Orange teams have conducted one repair every month," says Alain Polloni, head of submarine operations and maintenance at the France Telecom-Orange group.

Story continues below
advertisement

Immediately after the disruptions, alarms went off at the Orange Network Operating Centre located in Bagnolet, France. The NOC then sent out SMSes to the alert distribution list.

If cables on the ocean floor are liable to be damaged easily, there is a necessity to expedite the repairs as well. To do so, France Telecom-Orange, along with many other telecom operators and service providers operate ships across the world, in order to be able to rush technicians and experts to the sites of damage as soon as any network traffic is disrupted.

"When we have disruptions, cable faults are localised by the transmission and measurement of signals between station A and station B. This initial signal is electric and this is reassessed with the transmission tests that are conducted from the stations. With these we are able to exactly pinpoint the location of the failure," says Polloni.

Due to this constant vigilance brought about by the necessity to maintain customers, these companies have built up expertise in the area of repairing cables mid-sea in adverse conditions. But Polloni points out that each case can prove a challenge, regardless of the expertise at hand. And what happened on 19th of December last year, put the France Telecom-Orange group to the test.

Cable cut

On that particular day, six cables in the Mediterranean Sea off the coast of Sicily, Italy were cut. Cuts of these cables - SeaMeWe3 (SMW3), SeaMeWe4 (SMW4) and FLAG - had a direct impact on Orange's customer networks, cutting off traffic flow between Europe, the Middle East and Asia.

"Immediately after the disruptions, alarms went off at the Orange Network Operating Centre located in Bagnolet, France. The NOC then sent out SMSes to the alert distribution list. Our customers were informed real-time by our customer service centres worldwide," says Polloni.

He adds: "Based on our experience and because of the different localisations on the terminal stations of each cable, the almost certain preliminary diagnosis was a fault at sea probably in the same area and affecting several cables.

"This diagnosis was confirmed later in the same morning by the different measurements performed by terminal stations."

The job of traffic re-routing began as soon as there was information of cable damage. As only a branch of the SMW3 cable had been cut, traffic that could be restored off FLAG and SMW4 was routed through the main trunk of the SMW3 cable - the only immediately available route. In addition, Orange also called in its terrestrial network to restore some traffic to Asia and the Middle East.

Most network traffic heading ‘west' from the Middle East was diverted eastbound before heading back to Europe. In spite of these efforts, the need for rapid repairs loomed large, since the re-routing was causing longer round-trip delays and there remained some traffic that could not be re-routed at all.

To sea, ahoy!

Since these cuts affected most of the major carriers in the area, Orange conducted audio conferences and worked in close co-ordination with other members of the consortium to ascertain the priority of repairs on the cables. This done, it dispatched its cable repair ship Raymond Croze with 20km of spare cable from the French Riviera, to repair the SMW3 and SMW4 faults. Cable ship Teliri, which belongs to Elettra (an affiliate of Telecom Italia) was assigned to the FLAG repair.

"The network that we maintain makes us well prepared for such expeditions. We maintain ships in different parts of the Atlantic, Mediterranean Sea, Indian Ocean and North Sea. Additionally, we have all the data on these cable routes under the sea as well as the main operations of the various cables. We maintain this as sensitive information, and when we do need to conduct a repair we have all the information available," says Christian Brault, head of the network and traffic management centre at the France Telecom-Orange group.

Polloni adds:"When we have to conduct repairs on cable faults, when the ship is mobilised, we need to secure different things. We need to get enough spares aboard the ship to be assured the repair is performed in good time. We also need working permits if the cables are in territorial waters. We need to secure the terminal stations and make sure there is necessary staff to conduct tests during the repairs. These are the basic things to secure before the ship sets out."

Polloni adds that even when starting out, the team expected certain challenges in these repairs.

"Well, the major challenge that we face in undersea cable repairs is the condition of the sea itself. If the ocean is very rough and conditions are over operational limits it can lead to suspended repairs due to security reasons on board the cable ship. Though our ships are huge, and have capabilities to station and remain stable in rough conditions, there are always limitations.

In this particular project, the other major challenge was the fact there were multiple faults to handle. We had only two ships and six cables to repair. The order of repairs had to be agreed based on the volume of impact, and this had to be properly conveyed to the crew. If we have one cable to repair and one ship, things go smoothly. When we have multiple faults, things get complicated," explains Polloni.


| Share |


READERS' COMMENTS

Disclaimer: The views expressed here by our readers are not necessarily shared by ArabianBusiness.com or its employees.

Click here to post a comment


Add your Comment
All posts are sent to the administrator for review and are published only after approval. ArabianBusiness.com reserves the right to remove any comment at any time for any reason. Please keep your responses appropriate and on topic.
Arabian Business would like to point out that only comments relevant to the story will be published. Any containing personal insults or inappropriate language will not be approved.
Name *
Remember me on this computer
Email *
(Your email address will not be published)
City
Country
Subject *
Comment *
Notify me of further comments


Please click post only once - your comment will not be published immediately.


MORE FROM ARABIANBUSINESS.COM

From  Current Issue

SHARE PRICE CHECK

RELATED LINKS

  1. France Telecom-Orange group»

 EMAIL ALERTS

  1. France Telecom-Orange group

  2. Technology


Tell us your story

READER COMMENTS

  1. RTA to lease last batch of retail outlets on Red Line 05
    22 Nov ' 09 at 15:33
    Dont really know how well these outlets do. No feedback.   More  »
  2. The Roubini Vs Rogers debate 04
    22 Nov ' 09 at 14:44
    Simon, I agree with everything you say. The paper gold games of Comex and the gold fractional reserve banking system of the LBMA are...   More  »
  3. Dubai population grows 1.9% in Q2 03
    22 Nov ' 09 at 17:22
    nothing to do with sharjah and abu dhabi residents moving to dubai for better quality apartments or lower cost then?increased...   More  »

Read all user comments >

Gitex 2009

MORE FROM ARABIANBUSINESS.COM