Vue De Lac to begin this month
by This email address is being protected from spam bots, you need Javascript enabled to view it on Saturday, 04 July 2009
Under-performing partners, green regulations, and cash-strapped investors are among the factors that have caused serious delays to Al Attar Properties' Vue De Lac development in Jumeirah Lake Towers. Project manager Bipin Balakrishnan spoke exclusively to Construction Week about the trouble-plagued towers.
Al Attar Properties is in danger of redefining the word delay in its quest to build three towers in Dubai's Jumeirah Lake Towers (JLT) development.
The Vue De Lac towers, in plots K1, K2 and K3, were due for final handover in September 2007, almost two years ago. Today, foundation work is complete, but main construction is yet to begin, much to the chagrin of the project's investors.
But project manager Bipin Balakrishnan said last week that a new contractor - Goldline Contracting - had just been appointed, and insisted Al Attar was putting its troubles behind it.
"We terminated our contract with the original contractor because they were not performing," he said. "We saw they were not professional in their approach and lacked the experience in constructing such buildings."
The termination procedure took three months and the project was retendered. "We should be able to finalise the bank guarantee within a month," Balakrishnan said, "and then we will start construction."
The value of the new contract with Goldline was not revealed, but Balakrishnan said it had increased to accommodate green regulations.
But the lack of progress made by the original contractor begged the question: how did Al Attar know that the original contractor was not up to the task if it had not yet begun main construction, and why were they awarded the contract in the first place?
"We saw the preliminary drawings that had been submitted and knew they were not up to the task," Balakrishnan said. "They were awarded the contract because we had an old consultant in place at the time, and sometimes, the consultant has a binding agreement [with a contractor]," Balakrishnan added. "Sometimes that happens."
A new consultant, National Engineering Bureau (NEB), has since been appointed to the project.
Guarantees
So the big question: Could Balakrishnan guarantee that construction will begin this month? "By the end of this month maximum, the mobilisation will start," he said, but maintained that this was conditional on obtaining a bank guarantee.
Goldline Contracting chairman Dr Navjit Anand backed Balakrishnan when contacted by Construction Week saying, unprompted, that "this month we will begin construction."
So after battling with partners that were "not performing" and imposed green design changes, Al Attar must have thought the worst was over - when along came the global financial crisis.
"The bank guarantee has delayed us because nobody wants to put their fingers into the fire," Balakrishnan said. "The bank takes time to study the company and decide whether it is able to [provide a guarantee]."
Balakrishnan confirmed that the money that has been collected to date from investors was held in an Escrow account, though when asked if all of it was there, he replied, "As per the rules and regulations, whatever has to be done has been done and will be done. That is the scenario."
READERS' COMMENTS
Posted by salim, dubai, UAE on Sunday 6 September 2009 at 13:36 UAE time
I endorse the comment made by mohammed ashraf.I have invested in Toronto Project in 2004 which is next to Global Point.Handing over date was october 2007.since then once in 4 to 5 months an Project update appears stating"Approval received from Nakheel,Enabling works contract handed over"this statement being repeated since last 15-18months with only dates changing as update.I have seen around this Project no. of Projects coming up.it seems they don't have a will to Develop this Project.I request all the Investers in this Projects to comment & come forward to voice our concern.
Thank you.
Posted by duckman, dubai, UAE on Saturday 5 September 2009 at 12:59 UAE time
a single developer in the UAE that has been free from this sort of circumstances, i.e. project delivered on time at the cost promised, or else paid back the investors money in full.
Not surprising that Dubai reputation with foreign investors is what it is now.
Solution is straightforward and easy to implement,as it had been suggested here several times on AB. Why is no one listening, or acting upon it.
Posted by Mohammed Obaid, Dubai, UAE on Friday 4 September 2009 at 18:17 UAE time
This is not the first project that Al Attar have shown bad faith in. I invested in Global Point in 2004 - completion was due in October 2007. No work ever commenced despite numerous promises. In January we were promised full refunds in 6 months. The latest is maybe in 12 months time - and in installments. They have consistently gone back on their word and should be held to account. Please ask Bipin to comment on this!
Posted by Ashraf, Manchester, United Kingdom on Wednesday 2 September 2009 at 12:25 UAE time
Please could you ask Bipin when they will refund our money we paid for Global Point in 2004. It is 5 years and they have not even started the project. We borrowed from bank to pay for the project and are still paying the loan. I will appreciate your help
Thank you
Click here to post a comment
MORE FROM ARABIANBUSINESS.COM
TOP IN MIDDLE EAST CONSTRUCTION & INDUSTRY
TOP MIDDLE EAST BUSINESS STORIES
ALSO IN MIDDLE EAST CONSTRUCTION & INDUSTRY
SHARE PRICE CHECK
RELATED STORIES
Al Attar Properties
- Investors file case with RERA over Dubai project delays
22 Oct '09 | News - Vue De Lac to begin this week
27 Dec '08 | News




