ArabianBusiness.com - Middle East Business News
Sunday, 22 November 2009 19:36 UAE time

YOUR DIRECTORY /

| Share |

Construction disputes and the economic crisis

by David Dale on Saturday, 25 July 2009

David Dale discusses how the methods of resolving construction disputes are changing.

The Past

Only 12 months ago, if contractors and subcontractors experienced difficulties with their projects, they adopted a complacent approach to contractual disputes.

Story continues below
advertisement

During such times, poor record keeping and non-compliance with contractual administrative requirements were common. At the end of a project, ‘amicable negotiations' would take place and some contractors would be prepared to ‘take a financial loss' and simply move on to the next project and fund any losses by future advance payments; a vicious and dangerous circle of events.

There appeared to be no priority in preparing detailed and qualified tenders or carrying out risk assessments. Tender sums would be reduced, sometimes under pressure from employers, accepting that lowest price usually wins. One of the ways contractors reduced prices was by decreasing the amount of key project administrative and middle management staff. Acceptance of late payments against certified amounts, under valued variation costs, unsubstantiated employer back charges and non compensable extensions of time, appeared to be an accepted way of life for many.

Some employers did not seem to help this circle of events, by attempting to pass on contractual risk onto the contractors and  accepting the lowest possible price irrespective of a contractor's ability to deliver. In addition, there appeared to be an inclination to appoint an engineer or project manager who, in my experience, had little capability or resource to deal with, sometimes complex, contractual issues and disputes.

The Present

Nothing much has changed in terms of contractors' or subcontractors' willingness to reduce tender prices or to adopt better tendering and/or contractual administrative procedures. What seems to be changing is a resolve to pursue claims and make a firmer stand for what they consider to be their rightful entitlement. The number of disputes being referred to arbitration centres is on the increase. However, there is still an apparent reluctance to formally crystallise a dispute and to use the contractual mechanism for resolution, always assuming that one exists in the first place.

Many forms of informal alternative dispute resolution techniques seem to be used ahead of, for example, requesting a formal engineer's decision and giving notice of intent to arbitrate, without preparing a reasonably substantiated, particularised and credible claim.

Should such negotiations fail, contractors are left with no alternative but attempt to initiate legal or arbitration proceedings.  Unfortunately, once such a decision has been made, contractors often find themselves with problems in advancing any proceedings.

Legal fees will start to accrue with no guarantees of a successful award or even enforcement of such an award. There is therefore a point where the cost of preparing and prosecuting a claim becomes disproportionate to the amounts in dispute.

The Future

Contractors and subcontractors should learn valuable lessons from these experiences. Better qualified and priced tenders for new work combined with the requisite implementation of effective procedures run by suitably qualified staff is needed.

Employers on their part should endeavour to take a more balanced view of the commercial risk for their projects; passing the risk to contractors does not necessarily mean deliverance of a project on time and to budget.

Of course the above issues do not affect all employers, contractors or subcontractors.But the majority should consider a change in strategy as compliance with contractual procedures by all parties does not have to be adversarial and indeed should be positively encouraged.

The opinions expressed in this column are of the author and not of the publisher.

David Dale is partner and regional leader for contract solutions at international built asset consultancy, EC Harris, based in Dubai.

Having trained as a planning/industrial engineer, Dale has over 25 years' practical experience in project/commercial management in commercial real estate and in scheduling of major, multi-discipline projects world wide.

| Share |


READERS' COMMENTS

Disclaimer: The views expressed here by our readers are not necessarily shared by ArabianBusiness.com or its employees.
From the Employer’s perspective, I believe it reassure the same opinion
Posted by Shady Ateem, Dubai, UAE on Monday 27 July 2009 at 20:06 UAE time


After reading the above valuable discussion, I would like to add the following from my view point:

The Past: If Employers experienced difficulties with their projects, they adopted similar approach to that for the Contractors. The Employers had the barging power and enough liquidity to resolve raised disputes; moreover they were busy planning for the future projects. At that time nobody was focused on the Contractor’s claim contents and substantiation and everybody was oriented to go for the next step.

The Present: As for the current market situation; Employer’s start carefully studding the Contractor’s claims, lack of future projects and illiquidity situation adapted the Employer’s to think twice before releasing any payments or awarding compensable extension of time.

The Future: May be the Employers will gain back their barging power and liquidity, but they have already learned how to professionally deal with Contractors claims and defend their own rights. I believe disputes will never smoothly pass through like before.
Recovery Of Contractual Dues- Addressed to Mr. David Dale
Posted by Jennifer Grebe, Deira, U.A.E. on Monday 27 July 2009 at 13:24 UAE time


Exactly how does one get about recovering due which are pending for over a year and which the Main Contractor is avoiding to pay. I would appreciate an answer from Mr. Dale

Click here to post a comment


Add your Comment
All posts are sent to the administrator for review and are published only after approval. ArabianBusiness.com reserves the right to remove any comment at any time for any reason. Please keep your responses appropriate and on topic.
Arabian Business would like to point out that only comments relevant to the story will be published. Any containing personal insults or inappropriate language will not be approved.
Name *
Remember me on this computer
Email *
(Your email address will not be published)
City
Country
Subject *
Comment *
Notify me of further comments


Please click post only once - your comment will not be published immediately.


MORE FROM ARABIANBUSINESS.COM

From  Current Issue

SHARE PRICE CHECK

RELATED STORIES

EC Harris
| 3 stories
  1. UK firm secures $2m oil, gas contract in Saudi
  2. Maintaining MEP

RELATED LINKS

  1. EC Harris»

 EMAIL ALERTS

  1. EC Harris

  2. Construction & Industry


Tell us your story

READER COMMENTS

  1. RTA to lease last batch of retail outlets on Red Line 05
    22 Nov ' 09 at 15:33
    Dont really know how well these outlets do. No feedback.   More  »
  2. The Roubini Vs Rogers debate 04
    22 Nov ' 09 at 14:44
    Simon, I agree with everything you say. The paper gold games of Comex and the gold fractional reserve banking system of the LBMA are...   More  »
  3. Merger technical talks to conclude in a month - Emaar 03
    22 Nov ' 09 at 12:33
    Dubai needs is Antitrust & Trade Practices law in place to go forward.Too many people have burnt their fingers including large...   More  »

Read all user comments >

Gitex 2009

MORE FROM ARABIANBUSINESS.COM