ArabianBusiness.com - Middle East Business News
Thursday, 08 January 2009 02:53 UAE time

YOUR DIRECTORY /

Print this page Print this page | Email this to a friend Email this to a friend | Discuss this article (0 Comments) |

Rainfall hits on-site productivity in UAE

by ArabianBusiness.com staff writer  on Monday, 01 January 2007
Unexpected heavy rainfall throughout December meant contractors had to take temporary measures to waterproof MEP works.

The highest rainfall recorded in December in the last ten years has caused days of lost productivity in the Middle East’s MEP sector on site.

“In the last ten days we have lost about 20-25% production overall,” confirmed Ziad Taleb, MEP manager for Dutco Balfour Beatty-Al Ghandi & Consolidated Contractors Corporation JV at the Dubai Mall project.

“It affected the roofworks and work on the lower floors and we had some power outages on site. There was also some flooding on site because the site not sealed,” he explained.

Story continues below
advertisement

The installation of MEP services prior to buildings being weatherproof is common practice due to the normally dry climate in the region and many contractors were caught out by the persistance of the rainfall. By mid-December over 130mm of rain had been recorded, with more bad weather being forecast.

“We had to do some major temporary waterproofing on site,” explained Taleb. “We protected the expansion joints and purchased a lot of temporary submersible pumps to take the water from the site.”

Gareth Lucken, M.D. of Drake & Scull Industrial Water & power Division added: “We had to figure this into our operational plans over the last few weeks.

“It has slowed us down with the installation of infrastructure works such as cabling and pipework as it’s affected the civils works; operatives can’t weld pipes when the trenches are filled with water,” he reasoned.

In addition to protecting their own works, firms have been affected in other ways. Freddy Lama, M.D. of Nova explained: “We lost a lot of time on a particular site as the rain damaged a cable component board. That was important because [the line] is used to transmit a lot of information.”

Print Print | Email Email | Discuss this article |


READERS' COMMENTS


Click here to post a comment


Add your Comment
All posts are sent to the administrator for review and are published only after approval. ArabianBusiness.com reserves the right to remove any comment at any time for any reason. Please keep your responses appropriate and on topic.
Name *
Remember me on this computer
Email *
(Your email address will not be published)
City
Country
Subject *
Comment *
Notify me of further comments
Security Code * Code


Please click post only once - your comment will not be published immediately.


MORE FROM ARABIANBUSINESS.COM

From  Current Issue

RELATED LINKS

  1. Dutco Balfour Beatty»

 EMAIL ALERTS

  1. Balfour Beatty

  2. Drake & Scull

  3. Dubai Mall

  4. Dutco Balfour Beatty

  5. Nova Electromechanical

  6. Construction & Industry



Rich List 2008
EMIRATES ID DOWNLOAD

READER COMMENTS

Read all user comments >

BUSINESS FEATURES

Zero energy brighter future

A German architectural firm is to build the world's first tower with a zero carbon footprint in Bahrain.

Surging ahead

BMI forecasts Kuwait's construction industry to grow at 4.22% during 2008-12.

Bahrain's new island life

How will Bahrain's Amwaj Islands be affected by material problems and economic uncertainty?

BUSINESS INTERVIEWS

Leave only footprints

The UAE environment and water minister on how to reduce the country's ecological footprint.

Star attraction

Former international model and celebrity designer Kimberly Green gets ready to take on the Middle East.

The man behind the mosque

Aedas' Fariborz Hatam goes on record about building the mosque that has everyone talking.

MORE FROM ARABIANBUSINESS.COM