The crown jewel

by This email address is being protected from spam bots, you need Javascript enabled to view it  on Saturday, 17 October 2009

As the Princess Tower gears up to become the tallest residential building in the world, Construction Week looks at the progress on the 420m-high development and discovers what makes building a tall tower different from any other project.

There's no place like Dubai Marina to find a room with a view. With The Palm Jumeirah on one side and the city's bright lights on the other, it's no wonder that UAE developers are making their mark in the scenic location by constructing super-tall residential buildings.

In fact, building the tallest has almost become a competition in the area with 23 Marina and the Elite Residence Towers reaching new heights and set to stand at 90- and 91-storeys respectively upon completion. But, it is the Marina's Princess Tower that is set to reign as the tallest residential building in the world upon its expected completion date of July 8, 2011.

The project was first announced by Tameer Holding Investments in November 2006 and, three months later, Arabian Construction Company (ACC) was awarded the main construction contract. Work began immediately and the development, which will stand at 100 stories, has now reached the 58th floor.

Story continues below
advertisement

The Princess Tower consists of approximately 580 apartments. It has gymnasiums and swimming pools on levels five and six, and has six floors of parking below ground and four above.

There will also be some retail outlets facing Al Sufouh road and the side street running back to the marina. In addition, there will be a recreational area at level 97 for owners of the building and guests to enjoy the surrounding sights.

"Already the floor at level 57 is spectacular. It overlooks The Palm and the rest of the marina," says ACC project manager Bill Parker.

The tower is currently progressing five to six days ahead of the planned schedule but, according to Parker, the development hasn't always been a smooth process.

"With the financial crisis we had a slow down period but, together with the client, we have managed the process so that the project has continued to develop steadily through the period, albeit a little slower," he explains.

"We have a typical floor cycle of around six to seven days, but during the slowdown period we were completing a floor every two weeks. This was to help assist the client in managing its finances. In the last month, however, we have resumed full production, so we are now working towards completion."

However, there is more to building a skyscraper than simply constructing a few additional floors.

At the base of the Princess Tower, concrete elements are 130cm-thick and ACC is currently using 60cm-thick concrete at level 57; the contractor will later reduce the thickness to 30cm by the 100th floor. The building perimeter structure is progressively becoming thinner, so that the floors below can handle the load.

"Effectively, what we are doing with the very tall structure is constructing one building on top of another," explains Parker.

The composite slab is made up of steel beams, a corrugated metal deck and reinforced concrete with strengths of around 80 megapascals (MPa). The metal deck is stud-welded to the steel beams, so there is complete composite action, with rebar coming from the core and from the perimeter columns completing the slab.

"The slab acts as a diaphragm connecting the concrete core and perimeter columns. This structure system is known as ‘tube in tube' construction."

According to the project manager, Tameer chose ACC as the main contractor because of its expertise in very tall buildings. Parker himself also has a lot of knowledge in this particular field.

"I was involved in Eureka in Melbourne [Australia], which at the time was the tallest residential building in the world. This was completed in 2006 and I came to the UAE in the same year to join ACC," he says.

"I came from a tall building expert company and joined ACC for the specific task of building the next tallest building and the next after that."

It is because of ACC's specific construction knowledge that the Princess Tower is able to withstand seismic activity and damage caused by the elements.

Last month, S K Ghosh of S K Ghosh Associates, a seismic and building code consulting practice, told Construction Week that even in the Gulf, where there are few earthquakes, seismic provisions should be considered.

"There aren't many earthquakes in the Gulf but they are quite common in Iran and an earthquake there would definitely be felt out here," he said.


| Share |


READERS' COMMENTS

Disclaimer: The views expressed here by our readers are not necessarily shared by ArabianBusiness.com or its employees.

Click here to post a comment


Add your Comment
All posts are sent to the administrator for review and are published only after approval. ArabianBusiness.com reserves the right to remove any comment at any time for any reason. Please keep your responses appropriate and on topic.
Arabian Business would like to point out that only comments relevant to the story will be published. Any containing personal insults or inappropriate language will not be approved.
Name *
Remember me on this computer
Email *
(Your email address will not be published)
City
Country
Subject *
Comment *
Notify me of further comments


Please click post only once - your comment will not be published immediately.


MORE FROM ARABIANBUSINESS.COM

From  Current Issue

SHARE PRICE CHECK

RELATED LINKS

  1. Arabian Construction Company (ACC)»

 EMAIL ALERTS

  1. Arabian Construction Company (ACC)

  2. Construction & Industry


Tell us your story

READER COMMENTS

  1. Deal sought on Dubai World, Nakheel debts 11
    26 Nov ' 09 at 12:45
    While AB has a stated right to edit posts you should try to keep it to a minimum. Your editing took much of what I was trying to say...   More  »
  2. UAE real estate market has now hit bottom - analysts 06
    26 Nov ' 09 at 10:30
    this must be a new paradigm, Dubai flies in the face of natural economics.Lending money will not get easier. A credit induced...   More  »
  3. UAE banks need to improve customer service - poll 05
    26 Nov ' 09 at 09:11
    I recently had the same problem, having missed two credit card payments consecutively. Month one was due to having to pay a silly...   More  »

Read all user comments >

Gitex 2009

MORE FROM ARABIANBUSINESS.COM