| Home | GCC | World | Industries | Markets | Opinion | Interviews | Photos | Video | Lists | Lifestyle | StartUp | Topics | Jobs | Property | Smart TV |
Help, I forgot my username and/or password
The use of wind power has taken on a new form in Bahrain. Wind was traditionally used in the Middle East to cool buildings through natural ventilation wind towers, but in the newly constructed Bahrain World Trade Centre (BWTC) it will instead contribute to the electrical supply and operation. And in a world-first, the turbines used to capture the wind's energy have been fully integrated into the building structure.
Three 29-metre diameter wind turbines form the central feature of the BWTC. These are connected by nacelles to horizontal bridges, effectively tying together the two office towers of the BWTC. And at 50-storeys and 240m tall, the sail-shaped towers complete the dramatic and distinctive form of the building.
The elliptical plan and sail-like profiles of the towers have also been carefully designed to maximise the potential of the wind turbines. The towers are orientated to face the dominant prevailing onshore wind and their shape acts as aerofoils, effectively funnelling and accelerating the airflow between them and into the path of the turbine blades. The towers taper towards the top, their changing shape balancing with the increasing wind speed at height to ensure virtually equal wind speeds at all of the turbines.
Shaun Killa, chief architect with Atkins, proposed the design solution. "From the outset the project had as the basis of design the utilisation of conventional technologies and the development of a built form that would be sympathetic to receiving wind turbines," explains Killa. By adapting standard available wind turbines the premium on the project price of including the turbines was under 3% of the total project value. This compares favourably to Atkins' researched figures, which showed that this value could be 30% when using special turbines on large-scale building integration projects.
Wind tunnel testing was carried out to confirm the movement of the air around the towers and the availability of power. The structural shape will create an S-shaped airflow, with the centre of the airflow remaining almost perpendicular to the turbine. This increases the potential for creating power with the turbines and reduces fatigue on the blades. These tests were followed by computational fluid dynamic (cfd) modelling.
Engineering predictions by Atkins show that the wind turbines can operate in wind directions of 270-360°; however caution has been applied and initial operating regimes are based on a more limited range of 285-345°. At all wind directions outwith this range the turbines will automatically switch to standstill mode.
"Vertical axis turbines are not new technology waiting to mature, but have been known for a long time. There were a number of turbine manufactures that could supply 29/30m turbines," stresses Atkins senior project manager Simha LytheRao. The turbine blades and associated equipment were supplied as a complete package by Denmark-based Norwin. And in a truly international effort, the blades were manufactured by Danish firm LM Glasfiber in their India facility; the main gear and cooling system was from Germany; the generator from Finland; the main shaft is from the Czech Republic; and the control systems were from Denmark.
"[Norwin] was involved in the project from the very start and close co-ordination took place between the designer, supplier and contractor throughout the entire construction period and this work is still ongoing," stresses LytheRao. "The basic components of the turbines are identical to the ones you would find on any normal-mounted turbine, but the key structural components have been strengthened to increase safety and to ensure building user comfort," he adds.
Norwin and the main contractor Nass Murray & Roberts (NMR) carried out the installation of the turbines. "Large-scale turbines had never been placed at this height or between buildings before, which created new challenges," stresses LytheRao. The nacelles were lifted onto the bridges using a tower crane; this was carried out in parallel with the installation of the three bridges. The installation of the rotors followed this process. "The three blades used for each rotor were assembled on the ground and the entire rotor was lifted by tower crane into its final position and bolted to the main shaft," explains LytheRao.
"The lifting was NMR's scope, but under the supervision of Norwin; Norwin did the actual installation [of the turbines] when they were lifted into place," adds LytheRao. Cabling was within the scope of the main contractor, with the connection of cables between turbines and controllers carried out by Norwin.
"The main co-ordination issues relate to the services between the turbines and the buildings, including power cables, control cables, fire detection cables and chilled water pipes. As part of the ongoing co-ordination, the different interfaces were addressed and handled with the main MEP contractor," explains LytheRao.
All MEP installation services within the buildings and bridges, including all power cables for the wind turbines, is being carried out by the main MEP contractor, an EMCO Mercury joint venture. The lead-time for the turbines was 14 months, with the installation of the final blade being carried out in March 2007. Testing and commissioning of the turbines is scheduled to be undertaken within the next six months and they are expected to be operating on a daily basis after a further six months.
The electricity produced by the turbines will feed into the general electrical supply of the development. "Comprehensive ground tests indicate that the turbines will generate 11-15% of the energy requirements of the two towers," states LytheRao. "We have assumed that the turbines will operate on average for approximately 50% of the time over one year. This is under the provision that the buildings are able to consume the produced power," he adds.
Could you imagine what would happen if a large proportion of the educated, professional worker population suddenly left (let alone the domestic workers... more
Friday, 24 May 2013 1:26 PM - KhalidI was in Qatar yesterday and I had a good chuckle to myself about it all. There are three possible outcomes - all of which will be a monumental mess. ... more
Thursday, 23 May 2013 3:35 PM - SteveThe Saudi Govt been very cooperative and kind with Pakistan being the Muslim brothers and it will definitely a big big obligation for Pakistan and a hope... more
Saturday, 25 May 2013 12:40 PM - Muhammad AsifAs much as I love the UAE, this will be a problem for them in the future. Lets look at this from any democratic Country on Earth. If I decided not to turn... more
Wednesday, 22 May 2013 11:56 AM - Ty SayCould you imagine what would happen if a large proportion of the educated, professional worker population suddenly left (let alone the domestic workers... more
Friday, 24 May 2013 1:26 PM - KhalidIf one wants to visit or live in Bahrain one must abide by the laws. Living without pork is no huge sacrifice. Muslim and Jewish nations subscribe to this... more
Saturday, 25 May 2013 6:05 PM - Jeffrey Kershaw
Top managment greed is one of the main reasons that caused the 2008 crises. hope i delivered the message..
more
As much as I love the UAE, this will be a problem for them in the future. Lets look at this from any democratic Country on Earth. If I decided not to turn... more
Wednesday, 22 May 2013 11:56 AM - Ty SayCould you imagine what would happen if a large proportion of the educated, professional worker population suddenly left (let alone the domestic workers... more
Friday, 24 May 2013 1:26 PM - Khalid
Join the Discussion
Disclaimer:The view expressed here by our readers are not necessarily shared by Arabian Business, its employees, sponsors or its advertisers.
Please post responsibly. Commenter Rules