| Home | GCC | World | Industries | Markets | Opinion | Interviews | Photos | Video | Lists | Lifestyle | Topics | Jobs | Property | UOL |
Help, I forgot my username and/or password
The use of wind power has taken on a new form in Bahrain. Wind was traditionally used in the Middle East to cool buildings through natural ventilation wind towers, but in the newly constructed Bahrain World Trade Centre (BWTC) it will instead contribute to the electrical supply and operation. And in a world-first, the turbines used to capture the wind's energy have been fully integrated into the building structure.
Three 29-metre diameter wind turbines form the central feature of the BWTC. These are connected by nacelles to horizontal bridges, effectively tying together the two office towers of the BWTC. And at 50-storeys and 240m tall, the sail-shaped towers complete the dramatic and distinctive form of the building.
The elliptical plan and sail-like profiles of the towers have also been carefully designed to maximise the potential of the wind turbines. The towers are orientated to face the dominant prevailing onshore wind and their shape acts as aerofoils, effectively funnelling and accelerating the airflow between them and into the path of the turbine blades. The towers taper towards the top, their changing shape balancing with the increasing wind speed at height to ensure virtually equal wind speeds at all of the turbines.
Shaun Killa, chief architect with Atkins, proposed the design solution. "From the outset the project had as the basis of design the utilisation of conventional technologies and the development of a built form that would be sympathetic to receiving wind turbines," explains Killa. By adapting standard available wind turbines the premium on the project price of including the turbines was under 3% of the total project value. This compares favourably to Atkins' researched figures, which showed that this value could be 30% when using special turbines on large-scale building integration projects.
Wind tunnel testing was carried out to confirm the movement of the air around the towers and the availability of power. The structural shape will create an S-shaped airflow, with the centre of the airflow remaining almost perpendicular to the turbine. This increases the potential for creating power with the turbines and reduces fatigue on the blades. These tests were followed by computational fluid dynamic (cfd) modelling.
Engineering predictions by Atkins show that the wind turbines can operate in wind directions of 270-360°; however caution has been applied and initial operating regimes are based on a more limited range of 285-345°. At all wind directions outwith this range the turbines will automatically switch to standstill mode.
"Vertical axis turbines are not new technology waiting to mature, but have been known for a long time. There were a number of turbine manufactures that could supply 29/30m turbines," stresses Atkins senior project manager Simha LytheRao. The turbine blades and associated equipment were supplied as a complete package by Denmark-based Norwin. And in a truly international effort, the blades were manufactured by Danish firm LM Glasfiber in their India facility; the main gear and cooling system was from Germany; the generator from Finland; the main shaft is from the Czech Republic; and the control systems were from Denmark.
"[Norwin] was involved in the project from the very start and close co-ordination took place between the designer, supplier and contractor throughout the entire construction period and this work is still ongoing," stresses LytheRao. "The basic components of the turbines are identical to the ones you would find on any normal-mounted turbine, but the key structural components have been strengthened to increase safety and to ensure building user comfort," he adds.
Norwin and the main contractor Nass Murray & Roberts (NMR) carried out the installation of the turbines. "Large-scale turbines had never been placed at this height or between buildings before, which created new challenges," stresses LytheRao. The nacelles were lifted onto the bridges using a tower crane; this was carried out in parallel with the installation of the three bridges. The installation of the rotors followed this process. "The three blades used for each rotor were assembled on the ground and the entire rotor was lifted by tower crane into its final position and bolted to the main shaft," explains LytheRao.
"The lifting was NMR's scope, but under the supervision of Norwin; Norwin did the actual installation [of the turbines] when they were lifted into place," adds LytheRao. Cabling was within the scope of the main contractor, with the connection of cables between turbines and controllers carried out by Norwin.
"The main co-ordination issues relate to the services between the turbines and the buildings, including power cables, control cables, fire detection cables and chilled water pipes. As part of the ongoing co-ordination, the different interfaces were addressed and handled with the main MEP contractor," explains LytheRao.
All MEP installation services within the buildings and bridges, including all power cables for the wind turbines, is being carried out by the main MEP contractor, an EMCO Mercury joint venture. The lead-time for the turbines was 14 months, with the installation of the final blade being carried out in March 2007. Testing and commissioning of the turbines is scheduled to be undertaken within the next six months and they are expected to be operating on a daily basis after a further six months.
The electricity produced by the turbines will feed into the general electrical supply of the development. "Comprehensive ground tests indicate that the turbines will generate 11-15% of the energy requirements of the two towers," states LytheRao. "We have assumed that the turbines will operate on average for approximately 50% of the time over one year. This is under the provision that the buildings are able to consume the produced power," he adds.
This is not the right time to start launching studios, the economic situation in Europe is getting worse daily and is likely to create big ripples in UAE... more
Monday, 21 May 2012 2:15 PM - Red SnappaLet's see what will happen and if this project will go ahead. Only time will show. What happens to the other projects? not much is going on? Are investors... more
Monday, 21 May 2012 11:49 AM - Greg
That is probably one of the silliest moves that will hinder business and interaction.
Almost every company has dealings with some form of foreign entity... more
I find it amazing taht the very same people who 4 years ago were singing praises are today lamenting funeral wakes.
Business is a risk and about decision... more
What does "USA-tailored regime" and Iraq have to do with this story is beyond me. more
Monday, 21 May 2012 4:40 PM - Alithe majority of expats (as most people here argue that its a majority painting an entire nation the villain)....why are the filipinos and indians not the... more
Sunday, 20 May 2012 9:17 AM - ArthurIt is the Arabian Gulf because firstly Persia hasn't existed since 1935 and, therefore, does not appear on modern maps. So, by saying Persian Gulf we are... more
Sunday, 20 May 2012 7:40 PM - Juma Said JumaThis is not the right time to start launching studios, the economic situation in Europe is getting worse daily and is likely to create big ripples in UAE... more
Monday, 21 May 2012 2:15 PM - Red SnappaIn this part of the world, it will everlastingly be the Arabian Gulf because there is absolutely nothing persian about the Arabian Gulf. more
Monday, 21 May 2012 7:03 PM - Fahdseveral good points made here however democracy is about all the people and there are over 4 million people in Kuwait, Kuwaitis and expats we the expats... more
Friday, 18 May 2012 7:32 PM - jamesthe majority of expats (as most people here argue that its a majority painting an entire nation the villain)....why are the filipinos and indians not the... more
Sunday, 20 May 2012 9:17 AM - ArthurHOW CAN WE FORGET 2008, WHY DID YOU NOT FORGET TO PAY ALL YOUR STAFF BONUSES LIKE YOU HAVE DONE ON THE PAST TWO OCCASIONS , YET YOU CANT COMPENSATE OR... more
Wednesday, 16 May 2012 4:51 PM - MOOSAThe words one should read and think about are "it COULD make sense to sell Emirates in the future". Sir Flanagan does not say it does make sense at this... more
Thursday, 10 May 2012 11:16 AM - Paul dxbWhen I first went to live in ABu Dhabi - I clicked up a couple of speeding fines during the frist year (on empty roads and certainly not tailgating - but... more
Thursday, 17 May 2012 5:45 PM - BaffyNEVER BUY PROPERTY IN ARAB COUNTRIES !!! more
Sunday, 6 May 2012 6:37 PM - Rene
Join the Discussion
Disclaimer:The view expressed here by our readers are not necessarily shared by Arabian Business, its employees, sponsors or its advertisers.
Please post responsibly. Commenter Rules