Posted inEnergy

Saudi Aramco completes Karan gas project

Oil producer finishes commissioning remaining two gas processing lines at plant

(Bloomberg Images)
(Bloomberg Images)

Saudi Aramco has finished commissioning the remaining two gas processing lines of an expanded treatment plant for Karan, the kingdom’s first non-associated gas field, two industry sources said.

Gas from the offshore field will be processed at the Khursaniyah plant through three new production lines, known as trains, each with a capacity of 600m cubic ft per day (cfd).

In April, Saudi Aramco said it had brought online the first of the three new gas trains. It said then that the other two would be operational in the second quarter of the year, taking processing capacity to the target of 1.8bn cfd.

Aramco did not immediately respond to a Reuters request for comment on the successful commissioning of the last two units.

Follow us on

For all the latest business news from the UAE and Gulf countries, follow us on Twitter and LinkedIn, like us on Facebook and subscribe to our YouTube page, which is updated daily.